IEA estimates data center electricity consumption could double by 2030

Global data center electricity demand could reach approximately 1,000 TWh per year by 2030 due to the growth of artificial intelligence, the IEA forecasts.

cnbc.com

Data center electricity consumption increased by 17% in 2025, compared to a 3% growth in global electricity demand. Under the IEA’s Stated Policies Scenario, data centers are expected to use around 1,000 TWh per year by 2030.

The largest data center operators are expected to spend over $700 billion in 2026, primarily on new infrastructure. Major projects are being built in Texas, Virginia, Finland, and the United Kingdom. In some regions, the total capacity of facilities awaiting connection already exceeds current peak demand.

The IEA warns that without grid modernization, connecting new projects may be delayed, and generators may be forced to reduce output if grids cannot handle the load. Under the Stated Policies Scenario, 26 million km of new power lines will need to be built by 2035, and another 16 million km of existing lines will require replacement or reconstruction. Supplies of copper, cables, and transformers are already constrained.

The Stated Policies Scenario accounts for measures officially proposed by governments but not yet adopted. In this scenario, the share of electricity in global final energy consumption will rise from 23% to nearly 30% by 2035.